Installation of ETC ColorSource Dimmers and Enhanced Infrastructure
The Arnofini had ageing Thorn Dimmers and an urgent need for replacement. During liaisons and surveys with the Buildings and Facilities Manager, Push The Button discovered that the existing wiring had insufficient earthing and protection for a modern system. This eye to detail set Push The Button apart from competitors and led the customer to choose Push The Button to carry out the works, increasing the scope of works to resolve this earthing issue.
Push The Button delivered what was the first installation of the new ETC ColorSource ThruPower racks, where 6 x 24 Way racks were connected to the enhanced infrastructure. This work happened during the Christmas shutdown and enabled the incoming Bristol University Drama Department to use the new facilities straight after the Christmas vacation.